Bluecoat Academy

Brief description of works carried out:-
– Site wide reduced dig and formation for ground floor slab
– New storm and foul drainage system site wide including 2 Nr attenuation tanks
– Installation of building ground floor slab
– Installation of new gas and water services
– Installation of first floor slab to permanent formwork